Renovation Schedule

Mar 23 (prep) → Mar 28–Apr 6 (leave) → Apr 15 (flooring deadline)
Noisy
Quiet
Partner
Electrical
Drying
Milestone
Overall Progress 0 / 0

Gantt Chart Click a day for detail

Electrical Plan

Pre-leave (this week): Rough-in all cables, mount boxes, disconnect old fixtures. ~6-8h across evenings.

During leave: Route cables during gyprock (D1-D2), install fixtures after paint (D8-D9). ~4h total.

Cupboard Plan (Study)

Pre-leave Thu/Fri: Cut wall opening, frame recess (1.5m x 1.2m x 600mm), install rondo, mount gyprock, square set (tape + 1 coat). ~7h across 2 evenings.

During leave D8: Cut IKEA PAX to size + install. Square set will have 7+ days drying by then. ~3h.

Summary

Study
~30h
Bedroom
~34h
WIR
~18h
Stairs
~14h
Cupboard
~10h
Electrical
~10h
P1 Total
~116h
Bottleneck
Plaster drying

Purchase List Tick items as purchased